There’s a new dashboard in town folks. You asked about Phase 4?

The link for the new still being improved Capital Improvement Project (CIP) dashboard.

Be gentle though as it appears the new CIP Dashboard isn’t fully operational yet.

Here’s a link to a previous CIP Project Dashboard page: https://cipstatus.vbgov.com/ProjectDetail.aspx?id=4361.

Phase IV will dramatically upgrade Shore Drive in Ocean Park.

Moving sand around latest update

Thanks to Hank for getting the info from Dan Adams!

Staff is hammering out final scheduling details on some pending Bay Beach projects, here is the skinny:

Cape Henry Beach – A truck haul is planned to haul the sand stockpile form the Lynnhaven Dredge Material Management area to west end of Cape Henry Beach by truck. Approximately 70,000 yards of sand will be placed along the beach starting at the Point Chesapeake Gazebo. Dune reconstruction will occur in front of the high-rise condos where dune erosion has been most severe. Bids have been received and contract execution is underway. Public Notices will be sent out in the coming days with specific project start and schedule information. Work should start around mid-March and run through late May. The Jade St. beach access will be closed and/or restricted during this work.

A larger placement of approximately 150,000-200,000 cubic yards of sand along Cape Henry Beach is planned to occur Winter 23/24 as part of the USACE dredging of the Lynnhaven Federal Channel. This will be hydraulic (pipeline)dredging and placement. This project is schedule to advertise for bids fall of this and be awarded and executed in early 2024.

Chesapeake Beach Restoration – This project is for the renourishment of Chesapeake Beach from Little Creek Amphibious Base to Baylake Beach. The first nourishment was completed in May 2018 placing approximately 350,000 cubic yards of sand from a nearshore shoal to reconstruct a severely eroded beach and dune system. A renourishment is anticipated every 4-5 years to re-establish the design template and add advance maintenance sand for anticipated erosion. This first re-nourishment cycle will utilize the same sand source as the initial respiration project in 2018 and will be placed hydraulically(pipeline). The renourishment project will be advertised for bids this spring. To incentivize the number of interested bidders, a period of performance of 300 days is provided to allow contractors sufficient time to schedule and plan the work. The actual duration of the project should be closer to 4-8 weeks. The exact construction schedule will be determined after bids are received. A public information meeting and communication to the neighborhood and civic leagues will occur. Current status: Plans are 100% complete, final staff review and Q/C is underway. Bid dates will be established in the next week or two.

Ocean Park Beach –A contract is being prepared for dune grass and sand fence installation as follow on to compliment the beach restoration work completed last spring. This work will occur in March. The next placement and source of sand for Ocean Park will most likely be the next cycle of dredging of the Lynnhaven Federal channel in 3-4 years. Method of sand transport is hydraulic(pipeline).

Please let us know if BAC has any other questions at this time. We will include them on any public notices issued for the pending Cape Henry truck haul and Chesapeake Beach project.

Classroom with a view 🤓
Amazing Ocean Park beach. Thanks Public Works! 😁