Screen shot of construction cam on Nov 27 ’18 at noon.
Update from email:
Folks,
We are at a point where the last of the surface pavement is ready to be placed on the project. Beginning at on Tuesday, 11/27/2018 paving work will take place on WB Shore Drive between Page Avenue and East Stratford Road and is expected to be completed by 11/29/18. Since nighttime temperatures are expected to be below 40°F, this work will take place during the day between the hours of 9:00AM and 3:00PM. The paving schedule is as follows:
11/27/2018, 9:00 AM to 3:00 PM
WB Shore Drive between the Bridge and East Stratford Road (in front of 3556 On The Bay Condominiums)
Pave the LEFT TURN lane and the INSIDE thru lane on Shore Drive11/28/2018, 9:00 AM to 3:00 PM
WB Shore Drive between the Bridge and East Stratford Road (in front of 3556 On The Bay Condominiums)
Complete paving of the INSIDE thru land on Shore Drive then pave the OUTSIDE thru lane on Shore Drive and East Stratford Road (between Chesapeake House and 3556 On The Bay Condominiums)
WB Shore Drive between Page Avenue and the Bridge (in front of Overture Apartments)
Pave the INSIDE thru lane11/29/2018, 9:00 AM to 3:00 PM
WB Shore Drive between the Bridge and East Stratford Road (in front of 3556 On The Bay Condominiums)
Place permanent pavement markings
WB Shore Drive between Page Avenue and the Bridge (in front of Overture Apartments)
Pave the OUTSIDE thru lane11/30/2018, 9:00 AM to 3:00 PM
WB Shore Drive between Page Avenue and the Bridge (in front of Overture Apartments)
Place permanent pavement markingsThis schedule may change due to weather.
Please drive carefully when travelling this portion of Shore Drive!
-Chris
Christopher J. Wojtowicz, PE
Engineering Construction Manager
City of Virginia Beach
Department of Public Works
Engineering Division
2405 Courthouse Drive
Virginia Beach, VA 23456-9031
Office: (757) 385-5785
Fax: (757) 385-5668