#LESNERBRIGE update from Project Manager – “The large yellow girders for this gantry crane will begin to be assembled on the beach next week.”

May 19th 2015 update:

Friends and Fans of the Lesner Bridge Project:

The heat and beach weather have finally arrived, so you can officially put snow plows and ice and sand and salt out of your mind. Progress on the Lesner Bridge Replacement Project is moving onward, and we continue to receive a number of requests for information and updates – to which we gladly respond.

Below is the latest collection of facts and figures and other details – – updated for your reading pleasure – from Chris Wojtowicz, poster boy and mayor of “Wojo’s World.” Please give this a look when you have the time, and feel free to let Chris or me know if you have any questions or need more information.

As a reminder, we are regularly updating information on our WEB page at: http://www.vbgov.com/lesner-bridge. You can also follow us on Twitter at: @lesnerbridge.

If you know of someone who would like to be added to our update list, please have them get in touch with me at this e-mail address and I will be glad to add them.

Please feel free to pass this along to others. Thanks again for all of your patience throughout this project.

Enjoy the summer weather. . . AND STAY SAFE!

Drew Lankford
Media and Communications
Department of Public Works
City of Virginia Beach

dlankfor@vbgov.com
(O) 757.385.8062
(C) 757.409.4353

The bridge contractor has completed the erection of the temporary steel falsework between Pier #1 and Abutment A (this is near 3556 On The Bay condominiums) and has installed the support towers that the gantry trusses will rest on. The large yellow girders for this gantry crane will begin to be assembled on the beach next week. Once assembled, they will be moved to the temporary steel falsework to complete the assembly of the gantry crane.

image001-4

Temporary Falsework Tower Support at Pier #1

Pre-casting of the bridge segments at Atlantic Metrocast in Portsmouth, VA is now on a regular production schedule. 40 of the 177 bridge segments have been cast. In other words, we now have enough segments to complete 2 of the 10 spans in the westbound bridge and will likely have the third span complete by Memorial Day. As soon as the gantry crane is assembled, the contractor will begin delivering the segments to the project site.

The foundation work on the westbound bridge continues. All of the drilled shafts for Pier #4 have been installed and the Contractor is anticipating the completion of the drilled shafts at Pier #5 by 5/21/2015. There are 9 piers per bridge, therefore the Contractor is already past the halfway mark in the drilled shaft installation.

image002-3

Drilled Shaft Installation at Pier #5 (Temporary Trestle being assembled in background as preparation for foundation construction at Pier #7)

Over the next two weeks, the bridge contractor will;

Ø Mobilize the utility barges and drilling equipment to Pier #7 (east side of the Federal Channel in the Lynnhaven Inlet);

Ø Mobilize cranes to Abutment B (next to the former Duck Inn site) to prepare for driving piles for the abutment foundation and temporary retaining wall;

Ø Continue work on the temporary overhead crane installation at the Lynnhaven Dredge Material Storage Site;

Ø Dewater the cofferdam at Pier #3 and begin construction of the concrete cap at this pier location;

Please note, that when the Contractor begins installing the temporary retaining wall on the east side of Lesner Bridge next to Shore Drive he will have to temporarily close the outside lane of WB Shore Drive between Page Avenue and the bridge. All this work will be performed at night between the hours of 9:00 PM and 5:00 AM.

Through these project updates we’ve discussed a lot about the construction of the new bridges. Now as the project moves along we will be providing some information on the aesthetics of the new bridge – how the new bridge will look once complete. The new bridge will have a coating (TexCote® 300 Bridge Cote® ) Palomino Beige in color that will give the bridge a “finished” look as well as a protective layer to help protect the concrete from the elements as well as graffiti. The first application of this coating will be applied to the MSE wall near 3556 On the Bay Condominiums and Abutment A also located in this area.

image003

Bridge Coating – TexCote® 300 Bridge Cote® (Palomino Beige shown in upper left panel)

One last bit of information. We have posted a 3D animation of the bridge construction sequence on our website at http://www.vbgov.com/lesner-bridge The link is posted on the right side of the page under ADDITIONAL INFORMATION and is titled “Lesner Bridge Construction Sequence Animation”. This animation has been prepared using the expected sequence of construction to be used by the Contractor and shows – in scale – the relative size of the new bridges compared to the old bridges and how the traffic patterns will change over time as we move through the 5 phases of construction (we are in Phase 2 right now). We are also preparing a presentation that we will present periodically to the general public on the weekend. Dates and location have not yet been determined, but once we have the schedule we will post to the City’s website as well as send via this email update. This schedule and presentation will also be made available to the Bayfront Advisory Committee.

Drive Safely!

-Chris

Christopher J. Wojtowicz, P.E.
Project Manager
City of Virginia Beach
Department of Public Works
Municipal Center-Bldg 2
2405 Court House Drive
Virginia Beach, VA 23456-9031
Phone: (757) 385-5785
Fax: (757) 385-5668
email: cwojtowi@vbgov.com

Man helping ladies unload fish from a rented boat at Lynnhaven Inlet, circa 1948. This may be at Poole’s Marina.

Photo Credit: The New Tidewater Flashback Group in Facebook

Photo Credit: The New Tidewater Flashback Group in Facebook

Photo Credit from The New Tidewater Flashback in Facebook.

Thanks to Traycee for allowing us to share these!

Let us know in comments below if you’d like to see more flashback photos of the Shore Drive community.

Preserving precious live oaks at beloved LBR&BF and public safety

Some photos of recent pruning of live oaks at beloved Lynnhaven Boat Ramp & Beach Facility. 

IMG_8006

IMG_8009

IMG_8013

IMG_8016

IMG_8017

Planned is some cabling, a fence around both to strongly discourage climbing, which could lead to them being cut down for public safety reasons, plus signage with information about these live oaks.

Join us at our meeting this Monday where we will be discussing:

Proposed City Tree Task Force – SDCC is working with City Staff/Arborist to create a task force to discuss ways to help protect the City’s official tree (Live Oak) and maintain residential property rights.  Roadway encroachment lead to the planned removal of trees (200+ years old) at Shore Drive & Kleen St.

 

Charlie’s Seafood. Anyone know what year?

Photo Credit: The New Tidewater Flashback Group in Facebook

Photo Credit: The New Tidewater Flashback Group in Facebook

Photo Credit from The New Tidewater Flashback in Facebook.

Thanks to Traycee for allowing us to share these!

Let us know in comments below if you’d like to see more flashback photos of the Shore Drive community.

The COVB State of the Urban Forest Report is out and we get a C.

It is great see to the brutal honesty of the amount of work left to do to protect and increase our precious tree canopy.

Subscribe to The Advocate to learn more about what we'll be announcing soon to help

Subscribe to The Advocate to learn more about what we’ll be announcing soon to help

Start here to Subscribe to The Advocate – your resource for the latest news & info about the Shore Drive community.

Learn more about the Urban Forestry Management Plan, and the State of the Urban Forest Report at VBGov.com here.

The creation of this plan not only lays the framework for sustainable urban forest management in Virginia Beach, it indicates a high level of commitment to protecting trees and sharing knowledge about the important environmental, economic and social roles trees play in building healthy sustainable communities. The benefits of trees can be maximized when both professional management resources and an educated public coexist.

Protecting Pleasure House Point was used as a good example of what to do

Protecting Pleasure House Point was used as a good example of what to do

Gate 3, Little Creek Amphib. Base, Shore Dr., circa mid-’50s.

Photo Credit: The New Tidewater Flashback Group in Facebook

Photo Credit: The New Tidewater Flashback Group in Facebook

Photo Credit from The New Tidewater Flashback in Facebook.

Thanks to Traycee for allowing us to share these!

Let us know in comments below if you’d like to see more flashback photos of the Shore Drive community.

Sometimes all you have to do is ask for extra love. So we did. At the #LESNERBRIDGE.

Hooray for the new extra love for the City of Virginia Beach Official Tree at the beloved Lynnhaven Boat Ramp & Beach Facility!

We couldn’t understand why they weren’t already carefully marked off to protect them from the 3 year construction project – so we asked.

Orange fencing to add some extra visual cues for the hard working crews

Orange fencing to add some extra visual cues for the hard working crews

Orange fencing to add some extra visual cues for the hard working crews

Orange fencing to add some extra visual cues for the hard working crews

Love live oaks too?

Join Friends of Live Oaks today!

Live oaks are designated as the official tree of the City of Virginia Beach, and with good reason. Native to the area, live oaks were here long before European settlers. The tree is one of the most distinctive and recognizable plants in the city and immediately brings to mind our coastal areas and maritime ecosystem.

Chesapeake Beach Volunteer Fire Department

Photo Credit: The New Tidewater Flashback Group in Facebook

Photo Credit: The New Tidewater Flashback Group in Facebook

It is the view of the Chesapeake Bay Bridge Tunnel from atop a billboard that used to be behind the Chesapeake Beach Fire Dept. Photo Credit: Wally D.

It is the view of the Chesapeake Bay Bridge Tunnel from atop a billboard that used to be behind the Chesapeake Beach Fire Dept. Photo Credit: Wally D.

Photo Credit from The New Tidewater Flashback in Facebook.

Thanks to Traycee for allowing us to share these!

Let us know in comments below if you’d like to see more flashback photos of the Shore Drive community.

“Fire Department officials said Friday an underground power line shorted and caused the two-alarm blaze at The Dunes, Sunset Watch and Lesner Pointe East complexes along Page Avenue.”

Coverage at Pilotonline.com:

It could have been much worse, Fire Marshal Tassone said. The close proximity of the buildings helped the fire spread, but the wind was calm until after the fire was under control.

A fire at a condo complex on Shore Drive in Virginia Beach displaced more than 20 people on Thursday night, April 23, 2015. (Stephen M. Katz | The Virginian-Pilot)

A fire at a condo complex on Shore Drive in Virginia Beach displaced more than 20 people on Thursday night, April 23, 2015. (Stephen M. Katz | The Virginian-Pilot)

Coverage including video (that annoyingly starts with sound by default) and photos at 13 News Now.

Fireman trying to fight the flames at the Page Court condo fire on April 23, 2015. (Photo: Bobbi Sawyers?,13News Now viewer

Fireman trying to fight the flames at the Page Court condo fire on April 23, 2015. (Photo: Bobbi Sawyers?,13News Now viewer

Coverage including video at WTKR.com.

Fire at Page Court last night. “Two buildings are believed to be a total loss and three others were damaged.”

2 alarm fire located on Page Court just east of Lesner Bridge.
PageCourtScreenshot

Coverage at Pilotonline.com.

More than 20 people were displaced by a two-alarm condo fire overnight in the 2300 block of Page Court.

A fire at a condo complex on Shore Drive in Virginia Beach displaced more than 20 people on Thursday night, April 23, 2015. (Stephen M. Katz | The Virginian-Pilot)

A fire at a condo complex on Shore Drive in Virginia Beach displaced more than 20 people on Thursday night, April 23, 2015. (Stephen M. Katz | The Virginian-Pilot)

Coverage at WAVY.com includes video.

Six firefighters were injured battling an overnight fire that damaged 18 units in Virginia Beach and forced many residents out of their homes.

Coverage at WTKR.com includes “raw video” & photos.

Virginia Natural Gas and Dominion Virginia Power responded during the fire to secure a ruptured gas line and downed power lines.

Coverage at 13NewsNow.com including video & photos.

Ben L, who lives about 75 yards from the building where the fire started, said it was the scariest thing he ever saw. As he watched the flames move from building to building, he worried his would be next.

From a witness:

I was very proud to see a strong Ocean Park VRS response for this emergency. Two ambulances and three ALS providers, all from Ocean Park, plus a fantastic response from Company 1 and the VBFD. I saw Chief Cover on scene at 1am in his jeans helping out, and Chief McAndrews had it all under control. Three state of the art ladder trucks in the air with their master streams flowing was an awesome spectacle, and Support 8 with their volunteers arrived to assist with rehab and salvage. The Police kept a good perimeter and the neighbors kept a respectful distance and took in the displaced fire victims. There is a reason we have one of the top Emergency Response systems in the country, and this was a perfect illustration of how things can work well between agencies. Our EMS Chiefs on the scene kept us informed and safe, and Ocean Park even offered up shelter and food at the station for anyone that needed it, but there were no takers. I think the neighbors took care of their own! It is horrible when something like this happens, but I’m proud we can all come together and prevent the loss of life and further property.

Screenshot from #LESNERBRIDGE construction camera of photo from April 24 2015 1am.

Screenshot from #LESNERBRIDGE construction camera of photo from April 24 2015 1am.

Duck-In………What’s wrong with this picture??

Photo Credit: The New Tidewater Flashback Group in Facebook

Photo Credit: The New Tidewater Flashback Group in Facebook

Photo Credit from The New Tidewater Flashback in Facebook.

Thanks to Traycee for allowing us to share these!

Let us know in comments below if you’d like to see more flashback photos of the Shore Drive community.

Before and after photos of crane collapse at #LESNERBRIDGE

From the fancy construction camera.

Screen grab from April 13 2015 1pm construction cam zoomed in to 170%

Screen grab from April 13 2015 1pm construction cam zoomed in to 170%

CranecollapseSDCC

  

Duck Inn. Late 1970s, painting…….Shared by John Hartzog

Photo Credit: The New Tidewater Flashback Group in Facebook

Photo Credit: The New Tidewater Flashback Group in Facebook

Photo Credit from The New Tidewater Flashback in Facebook.

Thanks to Traycee for allowing us to share these!

Let us know in comments below if you’d like to see more flashback photos of the Shore Drive community.

#LESNERBRIDGE update from Project Manager – “On a final note . . . The Ocean Park Civic League is having a neighborhood yard sale this Saturday, April 11th,which means that there will be a lot of additional vehicles entering/exiting East Stratford Street at Shore Drive. Since our bridge contractor will also be working this weekend, please use caution on Shore Drive when nearing the East Stratford Street intersection and when turning onto East Stratford Street going towards the boat ramps.”

April 10th 2015 update:

Friends, Neighbors and Those Who Want to Know Everything About the Lesner Bridge Project:

As you sit outside on a gorgeous Friday and feel the bay breeze blow through your hair – or what’s left of it in some cases – treat yourself to the latest information about the Public Works project – the Lesner Bridge Replacement Project. Things are humming right along, and we are receiving a number of questions and requests for information on a regular basis – which is GREAT. We appreciate your interest and your comments about this important undertaking.

The latest collection of facts and figures and other details are below – updated for your reading pleasure or should someone suddenly begin to quiz you – as explained by Chris Wojtowicz, our project manager and the pride and joy of “Wojo’s World.” Please give this a look when you have the time, and feel free to let Chris or me know if you have any questions or need more information.

As a reminder, we are regularly updating information on our WEB page at: http://www.vbgov.com/lesner-bridge. You can also follow us on Twitter at: @lesnerbridge.

If you know of someone who would like to be added to our update list, please have them get in touch with me at this e-mail address and I will be glad to add them.

Please feel free to pass this along to others. Thanks again for all of your patience throughout this project.

Enjoy your weekend, and all the happenings our city offers . . . AND STAY SAFE!

Drew Lankford
Media and Communications
Department of Public Works
City of Virginia Beach

dlankfor@vbgov.com
(O) 757.385.8062
(C) 757.409.4353

Ok, let’s answer the first question that many of you have had or are thinking: “What is all that steel framework construction taking place in the dredge material storage area south of the Lynnhaven Boat Ramps?”

The answer is: The bridge contractor is preparing the storage area to receive the pre-cast bridge segments now being stored at Atlantic Metrocast in Portsmouth. This temporary steel framework will support an overhead crane that will be used to unload/load the bridge segments from the delivery trucks and move these segments within the storage area.

The bridge contractor has also been preparing the temporary steel falsework between Pier #1 and Abutment A (this is near 3556 On The Bay condominiums) to receive the support towers and gantry trusses. The two concrete pads recently poured at Abutment A is the foundation for one of the two towers that will be erected next week. These towers will be used to support the bridge segment assembly gantry.

Casting yard production of the bridge segments is also continuing. The expansion joint segment, which is the first segment that will be placed in the bridge (on Abutment A), was cast on Tuesday (the 7th). Three of the 14 typical segments for bridge span 2 have also been cast since the last project update.

(Expansion Joint segment with ~25% of steel reinforcing installed)

(Expansion Joint segment with ~25% of steel reinforcing installed)

The foundation work on the westbound bridge continues. The last of the ten drilled shafts at Pier #4 will be installed by today (Friday the 10th).

Over the next two weeks, the bridge contractor will;

Ø Mobilize the utility barges and drilling equipment to Pier #5 (east side of the Federal Channel in the Lynnhaven Inlet);

Ø Mobilize cranes to Abutment A to support the assembly of the bridge segment assembly gantry;

Ø Continue work on the temporary overhead crane installation at the Lynnhaven Dredge Material Storage Site;

Ø Install a cofferdam around the completed foundations at Pier #3;

Ø Install the new traffic signal poles and signal heads at the intersection of Shore Drive/Page Avenue/Vista Circle;

Ø Construct a haul road along the retaining wall adjacent to the Pointe Chesapeake property (former Duck Inn site) to support construction of Abutment B;

*** On a final note . . . The Ocean Park Civic League is having a neighborhood yard sale this Saturday, April 11th,which means that there will be a lot of additional vehicles entering/exiting East Stratford Street at Shore Drive. Since our bridge contractor will also be working this weekend, please use caution on Shore Drive when nearing the East Stratford Street intersection and when turning onto East Stratford Street going towards the boat ramps.

Because of all this activity, there will likely be more pedestrians and vehicles in this area this weekend than usual – so be alert and drive safely!

-Chris

Christopher J. Wojtowicz, P.E.
Project Manager
City of Virginia Beach
Department of Public Works
Municipal Center-Bldg 2
2405 Court House Drive
Virginia Beach, VA 23456-9031
Phone: (757) 385-5785
Fax: (757) 385-5668
email: cwojtowi@vbgov.com

Screen grab of zoomed construction cam shot taken on April 10th 2015 3pm.

Screen grab of zoomed construction cam shot taken on April 10th 2015 3pm.

Clyde’s Market on Shore Drive & West Great Neck Road

Photo Credit: The New Tidewater Flashback Group in Facebook

Photo Credit: The New Tidewater Flashback Group in Facebook

Photo Credit from The New Tidewater Flashback in Facebook.

Thanks to Traycee for allowing us to share these!

Let us know in comments below if you’d like to see more flashback photos of the Shore Drive community.

Markers for new beach trail at Pleasure House Point next to Brock Environmental Center pier vandalized.

Email from Lynnhaven River NOW sez:

Hey, everyone,

We started putting up the goose fencing for the planting sites along the trail at PHP, and came upon an unfortunate scene. Meredith had put in some fairly large stakes last week to mark the area, and they were all broken off today when we went out (stakes were thrown into the marsh area). We think maybe people think we are trying to block off the trails completely, and don’t understand that the path is simply shifting, though maybe they are just vandalizing for the sake of vandalizing. This was along the area where there is clearly still some type of ATV action.

IMG_3396

IMG_3390

IMG_3391

IMG_3395

Photo of stakes & goose fencing built by volunteers that was destroyed

Photo of stakes & goose fencing built by volunteers that was destroyed

Important phone numbers

Parks & Natural Areas Office: 757-385-2080
Police Non-Emergency Number: 757-385-5000
Animal Control: 757-385-4444

Still working on finding that sweet spot of eliminating 100% of vandalism & foolish behavior vs loving PHP to death.

Oyster bed in the Lynnhaven River…. 1986 VPA

Photo Credit: The New Tidewater Flashback Group in Facebook

Photo Credit: The New Tidewater Flashback Group in Facebook

YUM!

Photo Credit from The New Tidewater Flashback in Facebook.

Thanks to Traycee for allowing us to share these!

Let us know in comments below if you’d like to see more flashback photos of the Shore Drive community.

“Its for an overhead crane to move the bridge segments around the yard and offload from the delivery trucks.”

The new poles driven at the beloved Lynnhaven Boat Ramp & Beach Facility are for the #LESNERBRIDGE construction.      

#LESNERBRIDGE update from Project Manager – “Since our last update, the dredging of Crab Creek and the area in front of the wharf at the Lynnhaven Dredge Material Storage Site (LDMSS) has been completed.”

March 23rd 2015 update:

Aficionados of the Lesner Bridge Project:

This might be the first e-mail we’ve sent out in weeks that does not use the words “salt-and-sand solution” and “potholes,” and I consider that GOOD news. Chris rejoices below that “spring is in the air,” but I’m greedier . . . I want to see temps in the 90’s, AC’s running full blast and the sound of mosquitoes flying head first into my back yard zapper! That’s one of the best cures I know for these winter blahs.

The latest collection of facts and figures, updated for your reading pleasure, and other details are below, as explained by Chris Wojtowicz, our project manager and landlord of “Wojo’s World.” Please give this a look when you have the time, and feel free to let Chris or me know if you have any questions or need more information.

As a reminder, we are regularly updating information on our WEB page at: http://www.vbgov.com/lesner-bridge

You can also follow us on Twitter at: @lesnerbridge.

If you know of someone who would like to be added to our update list, please have them get in touch with me at this e-mail address and I will be glad to add them.

Please feel free to pass this along to others. Thanks again for all of your patience throughout this project.

Enjoy the week, and enjoy the approaching spring weather, AND our city. Stay safe.

Drew Lankford
Media and Communications
Department of Public Works
City of Virginia Beach

dlankfor@vbgov.com
(O) 757.385.8062
(C) 757.409.4353

Aaaahhhh . . . . spring is in the air! And with spring comes warmer temperatures that have the Lesner Bridge Replacement Project buzzing with activity!

Since our last update, the dredging of Crab Creek and the area in front of the wharf at the Lynnhaven Dredge Material Storage Site (LDMSS) has been completed. Much of the dredged beach-quality sand has to be stockpiled near this recently completed wharf, but some of this material was used to replenish Ocean Park Beach in preparation for the summer season.

As you have all noticed – the landscape at Lesner Bridge is beginning to change dramatically. Over the past several weeks, crews have been erecting the tall steel falsework on the west side of the bridge in preparation for assembly of the 300-foot long gantry crane that will be used to set the pre-cast concrete bridge segments into place. Assembly of this gantry will begin within the next few days, and will continue for several weeks.

unnamed-7

Completion of the gantry assembly will be in time for arrival of the first bridge segments to the project site. The 14 segments for the first bridge span have been cast and are currently being stored in the Atlantic Metrocast yard in Portsmouth.

The expansion joint segment and the pier segments are the only pieces remaining to be built before we can begin the assembly of these units in the new westbound bridge.
unnamed-8

Crews have made quite a bit of progress on other portions of the bridge work since the last update:

Ø Pier column #2 for the new WB bridge has been completed;

Ø 5 of the 10 drilled shafts for Pier #4 have been installed;

Ø Temporary trestle has been partially installed around the area of Pier #5;

unnamed-9

Over the next two weeks, work will increase on the east side of the bridge as we continue to build the retaining wall, temporary wire wall, and install storm drain/other utilities at this bridge approach. The remaining drilled shafts for the foundations at pier #4 will be placed thru 3/30/2015.

Along with all of these other activities, the contractor will also begin to assemble the temporary cofferdam around the previously installed drilled shafts at Pier #3 in preparation for the construction of the foundation cap.

That’s about it for this update.

Drive safely!

-Chris

Christopher J. Wojtowicz, P.E.
Project Manager
City of Virginia Beach
Department of Public Works
Municipal Center-Bldg 2
2405 Court House Drive
Virginia Beach, VA 23456-9031
Phone: (757) 385-5785
Fax: (757) 385-5668
email: cwojtowi@vbgov.com

Screen grab of construction cam shot taken on Feb 18th 2015 8am. Note: It was not spring.

Screen grab of construction cam shot taken on Feb 18th 2015 8am. Note: It was not spring.