#LESNERBRIDGE update from Project Manager – “Since our last update, the dredging of Crab Creek and the area in front of the wharf at the Lynnhaven Dredge Material Storage Site (LDMSS) has been completed.”

March 23rd 2015 update:

Aficionados of the Lesner Bridge Project:

This might be the first e-mail we’ve sent out in weeks that does not use the words “salt-and-sand solution” and “potholes,” and I consider that GOOD news. Chris rejoices below that “spring is in the air,” but I’m greedier . . . I want to see temps in the 90’s, AC’s running full blast and the sound of mosquitoes flying head first into my back yard zapper! That’s one of the best cures I know for these winter blahs.

The latest collection of facts and figures, updated for your reading pleasure, and other details are below, as explained by Chris Wojtowicz, our project manager and landlord of “Wojo’s World.” Please give this a look when you have the time, and feel free to let Chris or me know if you have any questions or need more information.

As a reminder, we are regularly updating information on our WEB page at: http://www.vbgov.com/lesner-bridge

You can also follow us on Twitter at: @lesnerbridge.

If you know of someone who would like to be added to our update list, please have them get in touch with me at this e-mail address and I will be glad to add them.

Please feel free to pass this along to others. Thanks again for all of your patience throughout this project.

Enjoy the week, and enjoy the approaching spring weather, AND our city. Stay safe.

Drew Lankford
Media and Communications
Department of Public Works
City of Virginia Beach

dlankfor@vbgov.com
(O) 757.385.8062
(C) 757.409.4353

Aaaahhhh . . . . spring is in the air! And with spring comes warmer temperatures that have the Lesner Bridge Replacement Project buzzing with activity!

Since our last update, the dredging of Crab Creek and the area in front of the wharf at the Lynnhaven Dredge Material Storage Site (LDMSS) has been completed. Much of the dredged beach-quality sand has to be stockpiled near this recently completed wharf, but some of this material was used to replenish Ocean Park Beach in preparation for the summer season.

As you have all noticed – the landscape at Lesner Bridge is beginning to change dramatically. Over the past several weeks, crews have been erecting the tall steel falsework on the west side of the bridge in preparation for assembly of the 300-foot long gantry crane that will be used to set the pre-cast concrete bridge segments into place. Assembly of this gantry will begin within the next few days, and will continue for several weeks.

unnamed-7

Completion of the gantry assembly will be in time for arrival of the first bridge segments to the project site. The 14 segments for the first bridge span have been cast and are currently being stored in the Atlantic Metrocast yard in Portsmouth.

The expansion joint segment and the pier segments are the only pieces remaining to be built before we can begin the assembly of these units in the new westbound bridge.
unnamed-8

Crews have made quite a bit of progress on other portions of the bridge work since the last update:

Ø Pier column #2 for the new WB bridge has been completed;

Ø 5 of the 10 drilled shafts for Pier #4 have been installed;

Ø Temporary trestle has been partially installed around the area of Pier #5;

unnamed-9

Over the next two weeks, work will increase on the east side of the bridge as we continue to build the retaining wall, temporary wire wall, and install storm drain/other utilities at this bridge approach. The remaining drilled shafts for the foundations at pier #4 will be placed thru 3/30/2015.

Along with all of these other activities, the contractor will also begin to assemble the temporary cofferdam around the previously installed drilled shafts at Pier #3 in preparation for the construction of the foundation cap.

That’s about it for this update.

Drive safely!

-Chris

Christopher J. Wojtowicz, P.E.
Project Manager
City of Virginia Beach
Department of Public Works
Municipal Center-Bldg 2
2405 Court House Drive
Virginia Beach, VA 23456-9031
Phone: (757) 385-5785
Fax: (757) 385-5668
email: cwojtowi@vbgov.com

Screen grab of construction cam shot taken on Feb 18th 2015 8am. Note: It was not spring.

Screen grab of construction cam shot taken on Feb 18th 2015 8am. Note: It was not spring.

COMMENT

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.