From an email:
Regarding Lesner Bridge:
Placement of the remaining sidewalks on the north side of Shore Drive between Page Avenue and East Stratford Road is taking place this week and will be completed by next Friday (11/16/2018).
On Sunday night (11/11/2018) between the hours of 9:00PM and 5:00AM, Public Utilities will be working in the inside lane of Shore Drive installing a valve into the new 16-inch water main located approximately 350 feet west of the Page Avenue/Shore Drive intersection. After this valve is installed, McLean is on schedule to pave westbound Shore Drive between the Page Avenue/Shore Drive intersection and the WB Bridge and between the WB bridge and the Shore Drive/East Stratford Road intersection. McLean anticipates the paving of Shore Drive to take place over two evenings, 11/15 and 11/16/2018. All required jackhammering will be performed during the day prior to the nighttime work.
Once this work is completed, only the landscaping and boardwalk remains to be completed for the Lesner Bridge Replacement Project.
Thank You,
-Chris
Almost done!

Screen shot of construction cam shot on Nov 9 9am