From email from Wojo:
I want to post another Bridge Update for today to alert folks what to expect during this evening’s traffic switch.
The traffic switch that will take place tonight, August 30th on Lesner Bridge will be performed in several stages with a lot of activity taking place at the intersections of Shore Drive/Vista Circle/Page Avenue and Shore Drive/East Stratford Road. Here are some additional details to let you all know what to expect.
Beginning at 8:00 PM this evening single lane closures will be set up at both the Shore Drive/East Stratford Rd and Shore Drive/Vista Circle/Page Avenue intersections. At this time Shore Drive will be reduced to A SINGLE LANE IN EACH DIRECTION as crews work in the intersections and median areas to eradicate old pavement markings and place the new ones. Workers will also be in bucket trucks adjusting traffic signal heads and preparing for the removal of the old traffic signal pole located at Shore Drive and Page Avenue.
Stage 1 of 8/30/2018 the Lesner Bridge Traffic Switch
PLEASE DRIVE CAUTIOUSLY through these two intersections while this work is taking place. Since there will be a short time that both traffic signals will be down while we switch to the new signals. During this time Virginia Beach Police will be assisting in maintaining the flow of traffic on Shore Drive on both ends of the bridge.
The single lane of eastbound Shore Drive traffic will be moved onto the new eastbound bridge once the new pavement markings have been placed. The westbound single lane of traffic will be maintained on the westbound bridge through this next stage of the traffic switch. Again, workers will be eradicating old pavement markings and placing new ones in preparation for the new traffic pattern.
Stage 2 of 8/30/2018 the Lesner Bridge Traffic Switch
Once all of the new pavement markings are down and the new traffic signals adjusted, the eastbound LEFT LANE will be re-opened to traffic and allowed to cross the new eastbound bridge. The LEFT LANE of the westbound traffic will also be re-opened and SHIFTED along with the RIGHT LANE to the southernmost lanes on the westbound bridge. THESE LANE SHIFTS WILL BE COMPLETED BY 5:00 AM FRIDAY, AUGUST 31st. Both bridges will remain in this traffic condition for the next several months while the new 10-foot wide multi-use path is built across the westbound bridge.
Stage 3 of 8/30/2018 the Lesner Bridge Traffic Switch
Pedestrians/cyclists who wish to use the new 10-foot wide multiuse path on the eastbound bridge located next to the new scenic overlook will be allowed to cross the new eastbound Lesner Bridge after 5:00 PM today, August 30th 2018, once crews finish sweeping and clearing the pedestrian areas. Please note that after the traffic switch, pedestrians will not be allowed to use the westbound bridge until construction of the new sidewalk/path is completed.
Finally, we want to make sure that everybody understands that the paving of the bridge approaches is not yet complete and that there may be some minor items of work taking place after the traffic is switched (i.e. painting, handrail adjustments, joint sealing, light adjustments, etc). The asphalt surface mix still has to be placed on both bridge approaches and is why you will notice a small lip of concrete along the concrete gutter pans and a small wedge of asphalt as you cross onto the concrete bridge deck. The pavement markings on eastbound Shore Drive at Vista Circle are also temporary and does not reflect what the ultimate travel lanes will look like once the project is complete (the RIGHT THRU LANE and RIGHT TURN LANE ONLY LANE have been combined into a single THRU RIGHT LANE). The reason for this is that we need still perform some median work before building out this fourth lane.
[This] figure shows how these lanes will look on eastbound Shore Drive at Vista Circle once we complete the project:
Finally, this is a word of caution to users of East Stratford Road who are leaving the Chesapeake House or 3556 On The Bay Condominiums. For the past several years drivers have gotten used to the temporary traffic pattern and have been making a LEFT TURN from southbound East Stratford Road onto eastbound Shore Drive and crossing the WESTBOUND LESNER BRIDGE. After this traffic switch drivers making this same LEFT TURN have pay attention to the new pavement markings and make sure that they enter eastbound Shore Drive and cross the EASTBOUND LESNER BRIDGE. Habits are sometimes hard to change, even with the new signage and pavement markings, so we just want to put this word of caution out there so that nobody ends up the wrong way on the westbound bridge!
PLEASE USE SLOW DOWN AND USE CAUTION TONIGHT WHEN TRAVELLING THROUGH THE LESNER BRIDGE CORRIDOR!
Have a Safe and Happy Labor Day Weekend!
-Chris
Christopher J. Wojtowicz, PE
Engineering Construction Manager
City of Virginia Beach
Department of Public Works
Engineering Division
2405 Courthouse Drive
Virginia Beach, VA 23456-9031
Office: (757) 385-5785
Fax: (757) 385-5668
Email: cwojtowi@vbgov.com