Jeremy can not attend so here is his report from an email:
+ + +
I have a conflict and can’t make the meeting today. I’m working with the city engineer on a project spreadsheet, I’ll keep you posted. Here are the updates from the PW side.
Chesapeake Beach Renourishment
Status
A contract has been awarded to Seaward Marine Corporation.
Work is underway and is to be completed by October 13, 2024.
Lynnhaven Inlet Dredging and Cape Henry Beach Placement
Status
USACE opened bids on April 3rd.
The work includes dredging the federal channel system, removing underwater debris, and placing the sand along Cape Henry Beach.
USACE intends to award the contract to Cottrell Dredging located in Norfolk, Va.
The most recent update from USACE indicated a pre-construction meeting and issuance of a Notice to Proceed sometime between late July and early August. From that point, Cottrell is required to submit a schedule within 15 days after NTP is issued.
Eastern Branch Lynnhaven River (EBLR) Dredging
Status
The City’s ongoing dredging project of the EBLR is going well with the contractor scheduled to complete Keeling Drain dredging this summer.
Crab Creek/Long Creek
Status
The next dredging cycle is being planned for winter 2024/2025.
Pleasure House Point Trail Breach
Status
Work has been completed to construct an elevated crossing over a flood-prone area.
These improvements will make the path more accessible after heavy rain events.
Comprehensive Safety Action Plan
Status
A draft of the City’s first Comprehensive Local Road Safety Action Plan will be publicly available for review and comment in August. The Plan identifies and prioritizes countermeasures to address roadway safety issues throughout Virginia Beach. Stakeholders, including members of the Bayfront Advisory Commission, were briefed on the Plan on March 22nd and provided feedback to staff on current safety challenges. Public Works Engineering staff will brief City Council on the Draft Plan on August 27th, and the Plan is anticipated to be adopted in September or October.
Lake Bradford / Chubb Lake projects
We typically do not provide updates to the BAC, but since the BAC provided support letters for the BRIC grant, we thought an update was needed.
Lake Pleasure House Outfall – construction complete
Lake Bradford Ditch Dredging – construction complete
Lake Bradford-Chubb Lake Stormwater Pump Station and Outfall
STATUS
The city is currently in the process of selecting a Design-Build team. The expected selection will take place in the first quarter of 2025.
The city applied for a Building Resilient Infrastructure and Communities (BRIC) Grant worth $35 million, but unfortunately, was not successful in receiving it.
Church Point-Thoroughgood BMP and Drainage Improvement – The City awarded the design contract to RK&K. Anticipated construction is in 2028.
STATUS
Design NTP – May 21, 2024
SCHEDULE
Advertise for Bids: February 2028
Estimated Construction Start Date: August 2028
Estimated Construction Completion: May 2031
Eastern Shore Drive Drainage Improvement Projects
Cape Henry Canal Phase II – Relocation of Sanitary Sewer Gravity Mains, 1C.2
The project was completed on October 2, 2023. The project was on time and Under Budget by $185,682.
Eastern Shore Drainage Improvements Phase I – Section I – $35.9M Building Resilient Infrastructure and Communities (BRIC) Grant Projects:
Eastern Shore Drive – Lynnhaven Colony Park Pump Station, 1B
Cape Henry Canal Phase II – Widening and Deeping, 1C.2
Eastern Shore Drive – Lynnhaven Drive Pump Station, 1D
Eastern Shore Drive – Elevate Lynnhaven Drive, 1E
STATUS
90% Design Completed January 2024 Project #1-3.
60% Design Completed March 2024 Project #4.
SCHEDULE
100% Design Submittal for all 4 projects – August 2024
Advertise for Bids: January 2025
Estimated Construction Start Date: May 2025
Estimated Construction Completion: May 2028
Eastern Shore Drive – Vista Circle Pump Station, 1A
STATUS
PER Completed. Project detailed design has not begun.
SCHEDULE
Advertise for Bids: October 2026
Estimated Construction Start Date: April 2027
Estimated Construction Completion: December 2029
Eastern Shore Drive – Poinciana Pump Station
STATUS
60% Design Submittal Received and compiling City and Peer Review Comments
SCHEDULE
Advertise for Bids: April 2025
Estimated Construction Start Date: August 2025
Estimated Construction Completion: May 2028
Eastern Shore Drive – North Shore Drive Street Drainage Improvements, 1F & Eastern Shore Drive – Cape Henry Drive Street Drainage Improvements, 1G
STATUS
60% Design Submittal Received March 2024
SCHEDULE
Advertise for Bids: June 2025
Estimated Construction Start Date: September 2025
Estimated Construction Completion: June 2027
Shore Drive Corridor Improvements Phase III
STATUS
No change. Real estate acquisition and private utility relocations are underway.
SCHEDULE
Advertise for Bids: September 2024
Estimated Construction Start Date: January 2025
Estimated Construction Completion: July 2028
Shore Drive Pedestrian Improvements
STATUS
90% Design Submittal Received July 2, 2024
SCHEDULE
Advertise for Bids: June 2025
Estimated Construction Start Date: October 2025
Estimated Construction Completion: April 2026
Shore Drive Corridor Improvements Phase IV
STATUS
No change. Final Preliminary Engineering Report received 11/15/2023. The project is not funded
Jeremy Kline
DEPARTMENT OF PUBLIC WORKS
Deputy Director
757.385.8420 | jekline@vbgov.com
+++

Work is underway and is to be completed by October 13, 2024.
Is there an update to this completion date? If so, what is the new date?
Not yet. We’ll provide when we get it.