Johnson assured the Commission that funding for the $29.1 million project would not be diverted to other CIP projects. Part of the reason for additional design stemmed from staffing difficulties in the wake of the May 31, 2019, mass shooting at Building 2 in the municipal complex, he said. This resulted in relocating Public Works Department offices, equipment and workers along with turnover due to retirements and transfers.
Another part of the Shore Drive improvements, Phase IV (CIP 2-118), between Marlin Bay Dive and the Lesner Bridge was paused after concept design was completed in 2008. Design is planned to resume next year with a projected March 2024 construction start. Funding for this $15.5 million phase is #1 to the BAC’s high-priority 2019-20 strategic plan.
News includes 18 month delay for Phase 3, Phase 4 delayed again, City seeks public input into Comp Plan & Fire Department services and more.