Update from Email:
Folks:
Last week we successfully accomplished a major milestone in the project – moving the gantry crane from the north side of Shore Drive to the south side of Shore Drive and into position to begin assembly of the eastbound bridge superstructure segments. To do this, we had to close Shore Drive and setup a long detour until the move could be completed. The last piece of this move is to remove the two beams that are currently located on the western end of the bridge crossing Shore Drive.
Unlike the first two phases of this gantry crane move, a detour WILL NOT be required to remove these two beams. NEXT Thursday July 6th, beginning at 12:01 AM and ending at 4:00 AM – Shore Drive at Lesner Bridge will be reduced to a single lane and a flagger operation will control the direction of traffic across the bridge. Therefore, motorists should be PREPARED TO STOP on their approach to the bridge during this time period.
Bridge crossing delays of up to 15 minutes should be expected and motorists may want to plan an alternate route while these two beams are removed.
Area of Work and Restricted Traffic on Lesner Bridge July 6, 2017 12:00 AM to 4:00 AM
Please note that on Wednesday July 5th, beginning at 10:00 PM Shore Drive at Lesner Bridge will be reduced to a single lane in each direction in preparation for the flagger operation that will begin at midnight.
We appreciate your patience regarding these traffic interruptions along Shore Drive at Lesner Bridge!
Have a Happy and Safe Independence Day! …and of course Please Drive Safely!
-Chris
Christopher J. Wojtowicz, PE
Project Manager
City of Virginia Beach
Department of Public Works
Engineering Division
2405 Courthouse Drive
Virginia Beach, VA 23456-9031
Office: (757) 385-5785
Fax: (757) 385-5668
Email: cwojtowi@vbgov.com