#LESNERBRIDGE update from Project Manager – “NO, that big yellow and blue structure being erected now is NOT part of the bridge.”

July 16th 2015 update:

Esteemed Lesner Bridge Fans and Followers:

Hope everyone is enjoying the season of hot weather, cold drinks, baseball and lots of beach and vacation time. Soak it up and savor the summer days that come with living in our little corner of paradise!

Progress on the Lesner Bridge Replacement Project is moving onward, and you can see the progress almost on a daily basis.

Below is the latest collection of facts and figures and snappy photos – updated for your reading pleasure – from pretty face Chris Wojtowicz, project manager and captain of our “launching gantry crane.” We offer compelling reading in this update, so please add this page turner to your paperbacks and magazines for your pool and beach reading.

Feel free to let Chris or me know if you have any questions or need more information.

As a reminder, we are regularly updating information on our WEB page at: http://www.vbgov.com/lesner-bridge. You can also follow us on Twitter at: @lesnerbridge.

If you know of someone who would like to be added to our update list, please have them get in touch with me at this e-mail address and I will be glad to add them.

Please feel free to pass this along to others. Thanks again for all of your patience throughout this project.

Enjoy the summer weather, keep zapping those skeeters . . . AND STAY COOL AND SAFE!

Drew Lankford
Media and Communications
Department of Public Works
City of Virginia Beach

dlankfor@vbgov.com
(O) 757.385.8062
(C) 757.409.4353

**************************************

Folks:

Before we get started on all details of the most current bridge construction progress – let us answer one question that everyone has been asking: NO, that big yellow and blue structure being erected now is NOT part of the bridge.

This structure is actually a launching gantry crane that will be used to set the segments for each span of the new bridge. You can see how this equipment will be used in the Lesner Bridge Construction Sequence Animation The elevation of the new bridge deck will be about where the feet on the blue gantry roller supports now rest. This equipment is very unique and is manufactured by Deal who designs and builds this specialty equipment for bridge construction now being done all over the world. Please check out their website for more information.

Now for the progress update on the bridge construction.

The segment launcher and gantry crane continues to be assembled between bridge piers 1 and 2 and is expected to be completed in approximately 3 weeks. Since the last update, crews have completed the construction of the footing and column for pier #3, finished the drilling of all shafts at pier #7, mobilized material and equipment to pier #6 for drilled shaft installation, and have installed all of the piles for Abutment B (next to the former Duck Inn site) of the new WB bridge.

Completed Bridge Column and Footing at Pier 3 (formwork to be removed at a later date)

Completed Bridge Column and Footing at Pier 3 (formwork to be removed at a later date)

Seal Slab and Footing Formwork Being Assembled and Readied for Placement at Pier 4.

Seal Slab and Footing Formwork Being Assembled and Readied for Placement at Pier 4.

The assembly of the unloader gantry next to the Lynnhaven Boat Ramps was also completed since the last update. With the completion of the unloader gantry, completed bridge segments have begun arriving at the construction site with a total of 10 delivered to date. Once the segment launching gantry is completed, these delivered segments will be moved to the beach beneath the launching gantry and then be lifted into place. It is expected that the first segments for bridge span 1 will be lifted into place sometime during the first week of August 2015.

Pre-cast Concrete Segments for the New Lesner Bridge stored at Lynnhaven Dredge Material Storage Area

Pre-cast Concrete Segments for the New Lesner Bridge stored at Lynnhaven Dredge Material Storage Area

AMI, Inc in Portsmouth, continues to build the new bridge segments. A total of 59 of the 177 bridge segments have been cast and is enough to complete 3 of the 10 spans in the westbound bridge. The pre-casting of span 4 of the bridge is also nearly complete with only 6 segments remaining to be cast to complete the span.

Over the next two weeks, the bridge contractor will:

Ø Complete the footing construction for Pier #4;

Ø Complete drilled shaft installation at Pier #6;

Ø Mobilize material and equipment to Pier #8;

Ø Begin formwork installation for Abutment B;

Ø Install concrete finish coping along the top of the MSE wall next to 3556 On The Bay Condominiums;

Ø Complete wooden fender installation at the wharf next to the Lynnhaven Dredge Material Storage Area

That’s it for now.

Drive Safely!

Christopher J. Wojtowicz, P.E.
Project Manager
City of Virginia Beach
Department of Public Works
Municipal Center-Bldg 2
2405 Court House Drive
Virginia Beach, VA 23456-9031
Phone: (757) 385-5785
Fax: (757) 385-5668
email: cwojtowi@vbgov.com

Screen Shot of Construction Cam photo taken 2015-07-17 at 8.05.17 AM

Screen Shot of Construction Cam photo taken 2015-07-17 at 8.05.17 AM

COMMENT

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.