Sand move from LBR to Cape Henry Beach complete!

From Jim:

There is some cleanup to do at the beach and the contractor is completing the construction of the perimeter dike at the DMMA site. The cleanup and equipment removal at the beach should wrap up this week. The perimeter dike at the DMMA site will be completed by mid-August.

Facts about the project:
+Sand hauling to Cape Henry Beach began on May 2, 2023
+Sand hauling to Cape Henry Beach was completed on July 26, 2023
+Cape Henry beach was nourished between the Point Chesapeake +Condominium gazebo and just west of the Jade St beach access (approximately 1,800ft in length)
+Volume of sand placed within the Cape Henry Beach project limits = 70,200cys (or 38cys/ft)
+Number of trucks that hauled the sand = 5,220
+Average trucks per day = 93
+Average volume of sand transported in a single truck load = 13.5cys
+The base elevation at the DMMA site is +10ft above sea level
+The highest elevation at the DMMA site prior to the start of construction was +35ft above sea level
+The new sand perimeter dike at the DMMA site will have a crest elevation of between +15ft and +18ft above sea level

A successful project!