Hello Shore Drive Community,
The following emails are updates from our friendly neighborhood Project Engineer regarding the repaving of areas that have recently had stormwater improvements completed. It looks like paving of these areas is scheduled to be finished by the end of July.
Stay safe and stay healthy,
Todd
Dear SDCC,
An update for you on the some of the “rough-rides” you may be experiencing at Starfish Rd and N. Great Neck Rd.
Good news for these asphalt issues. We are trying to be fair to the contractor and limit his mobilization of final Asphalt surface course construction to two occurrences. The reason it is riding a little rough is because intermediate course has been placed on top for now, and yes, there are noticeable differences in elevation at the edge points that create a bump. The contractor is working at Red Tide Rd right now, and after he completes the storm sewer construction, we will then be milling (pavement planning) the asphalt down at Starfish Road, North Great Neck Road, the Cape Henry canal Trail and Red Tide Road. Then a complete overlay of surface course asphalt will be placed back in accordance with the Contract Documents.
At N. Great Neck Road, we are going to slightly beyond the limits of the trench excavation to make sure there is “no bump” and mill out the asphalt to only the right turn lane (northbound) and merging lane (southbound). But the future Shore Drive Phase III roadway project in a couple years (100% design) will be providing a complete intersection pavement rebuild along with that project. For Starfish Rd and Red Tide Rd, it will be complete face-of-curb (edge-of-pavement)) to the other face-of-curb (edge-of-pavement).
All This work will be completed by July.
The second mobilization of asphalt surface course will occur after the heavy construction at West Great Neck Road and Cape Henry Drive in the summer and fall.
Best Regards,
Brad
Bradley W. Vanderwarker, P.E.
Project Manager
City of Virginia Beach
PW/Stormwater Eng. Center
2473 N. Landing Road, Building 23, Room 139
Virginia Beach, VA 23456
(757) 385-4131 (main)
(757) 385-8556 (direct)
(757) 705-7507 (cellular)
bvanderwarker@vbgov.com
Additional details of the work being done on the Cape Henry Trail. A plan of the work location can be seen by clicking here Cape Henry Trail Milling & Surface Course Overlay
Todd/Tim,
The milling and resurfacing of the Cape Henry Trail between W. Great Neck Road and N. Great Neck Road is graphically displayed in the attached.
This will provide a nice smooth trail system from the major construction at W. Great Neck Road over and through where the large 76”x48” Culvert behind the Fire Station was recently constructed. It ends just west of Sunstate Ct. where shown. It was not in the scope of this project to repair and resurface the trail to the east over to Beech Street.
Even with the localized construction at N. Great Neck Road, we are only repairing a localized section of the stamped brick area on the west side of N. Great Neck Road.
Further questions relative to the Cape Henry Trail program may be directed to Elaine Linn elinn@vbgov.com with Parks & Rec.