Dredging of Inlet and Replenishment of Cape Henry Beach Complete. Dredging of Broad Bay Channel Started

The following is taken from an email update provided by the project coordinator….

It does not look like the Contractor will make it to Oak Street given the remaining volume they have in the turning basin in the re-dredge areas. Will have a better idea of things when I receive their daily report from today’s operations. They are quickly finishing up these areas and following the Government’s acceptance of the dredging work (may take about a week plus a couple of days max), will remove pipeline from Cape Henry Beach and be complete with this placement area.

Long Creek dredging will not be a part of this contract. We have a few dredging areas within Broad Bay Channel. The material from these dredging areas will be going to our upland placement site at Maple St. The site has been prepped to receive material and dredge pipeline is in place to being dredging in Broad Bay Channel. These operations will begin soon following the Contractor’s completion of dredging in the Basin. This will be 24/7 operations with specifications that the contractor, to the maximum extent practicable, limit or try to reduce noise from 7PM – 7AM.

There will be a dredge pipeline in Long Creek to transport dredged material from the Broad Bay Channel dredging areas, but this will be the only thing operational in Long Creek.

Please let me know if you have any questions.

Regards,
Chris

Christopher B. Tolson
Design Section, Operations Branch
Norfolk District, U.S. Army Corps of Engineers
Office: (757) 201-7012

COMMENT

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.