The following is taken from an email update provided by the project coordinator….
It does not look like the Contractor will make it to Oak Street given the remaining volume they have in the turning basin in the re-dredge areas. Will have a better idea of things when I receive their daily report from today’s operations. They are quickly finishing up these areas and following the Government’s acceptance of the dredging work (may take about a week plus a couple of days max), will remove pipeline from Cape Henry Beach and be complete with this placement area.
Long Creek dredging will not be a part of this contract. We have a few dredging areas within Broad Bay Channel. The material from these dredging areas will be going to our upland placement site at Maple St. The site has been prepped to receive material and dredge pipeline is in place to being dredging in Broad Bay Channel. These operations will begin soon following the Contractor’s completion of dredging in the Basin. This will be 24/7 operations with specifications that the contractor, to the maximum extent practicable, limit or try to reduce noise from 7PM – 7AM.
There will be a dredge pipeline in Long Creek to transport dredged material from the Broad Bay Channel dredging areas, but this will be the only thing operational in Long Creek.
Please let me know if you have any questions.
Regards,
Chris
Christopher B. Tolson
Design Section, Operations Branch
Norfolk District, U.S. Army Corps of Engineers
Office: (757) 201-7012