In case you’re keeping track, here’s the numbers you want to follow improvements for Shore Drive:
CIP Project Updates:
· Shore Drive Interim Safety Improvements (2-731): Slideshow attached summarizing work completed to date
· Shore Drive Demonstration Project (2-115): Completed 2008
· Shore Drive Phase II (2-116): Currently at 30% design, project is on hold due to funding
· Shore Drive Phase III (2-117): Currently at 30% design, project is on hold due to funding
· Shore Drive Phase IV (2-118): Currently at 30% design, project was funded for construction in 2012, however this may be delayed to 2016. This is Ocean Park area. Marlin Bay > Lesner Bridge.
· Lesner Bridge Replacement Project (2-168): Approaching 90% design, no funding for construction or utility relocations