Grace,
As of this morning, 7 of the 9 Beach Accesses are substantially complete and currently being utilized by the public.
Whaler Ct. will be completed today – remaining work is debris clean up.
Sandalwood Rd. & Great Neck Rd. Accesses – Still waiting for the railing fittings to be delivered to install the ADA handrail & non-skid strips on the ramping at Sandalwood Rd. and the steel handrail and fittings at Great Neck Rd.
Velzey Ave. – Construction to begin tomorrow and should be completed by this weekend.
Delays have been due to specialized material deliveries from manufacturers and , specifically this week, contractor equipment breakdown.
Should you have any additional questions or concerns, please contact me at your earliest convenience.
Very truly yours,
Karl L. Smithson, APM
PW/Operations – Technical Support
385-1540 (Office)
403-3821 (Cell)